Tooling, material, labour and freight, priced at the quantity you will actually buy. A 300-piece case costs 2.2 times a 2,000-piece case, and most of that gap is amortisation.
A hard case quote contains four or five numbers, and buyers usually compare the last one. The unit price is an output: it depends on tooling amortisation, the specification of the shell and the quantity you are actually going to buy. Pull those apart and a quote becomes auditable.
What follows is the cost model we use for a custom EVA case, with the ranges we see for a medium case at 300 and at 2,000 pcs.
Separate one-off costs from per-piece costs
Two buckets. One-off money is paid once per design: the compression mould, the die-cut insert tool, the logo plate. Per-piece money scales with the order: EVA sheet, face fabric, lining, zipper, labour, packaging. Freight and duty sit underneath both, because they scale with the shipment rather than with the design.
Mixing the buckets is why a 300 pcs order feels like a bad deal. Against 2,000 pcs, the unit price is 19% higher, the tooling per piece is 6.6 times higher, and the landed cost per case is 2.2 times higher — three different stories from the same quote. A US$1,360 tooling bill is US$4.53 per case at 300 pcs and US$1.36 at 1,000: same money, different denominator.
Tooling: mould, die and logo plate
- Compression mould, US$600–1,400. One cavity, cut to your shell geometry. Aluminium covers 5,000–20,000 pcs; steel costs more and is worth it above that. Lead time 15–20 days, and the charge is credited against orders of 2,000 pcs or more.
- Die-cut insert tool, US$150–300. A steel-rule die bent to the device outline, good for 5,000–10,000 strikes. Lead time 3–5 days, and it is a separate tool from the shell mould.
- Logo setup, US$80–200. An embossing plate, a screen frame or a heat-transfer die. Lead time 2–4 days. A second colour or a second logo position means a second setup.
New case, new tooling: US$830–1,900. On a cavity already in the 300+ mould library: US$230–500, because the mould line drops to zero and only the die and the logo plate remain.
A mould that comes out 3 mm short in depth cannot be fixed by adding foam: the shell either closes on the product or leaves a gap the insert has to absorb, and the insert is not a spring. A recut is a second US$600–1,400, which is why the 15–20 day sampling window includes a dimensional check on the first pressing rather than only a look at the finish.
Material: where US$1.10 to US$4.80 comes from
At 1,000 pcs a 5 mm 75D EVA shell blank costs US$0.55–0.95 depending on surface area. The face adds 600D at US$0.25–0.40, 1680D at US$0.55–0.85, or 0.8 mm PU leather at US$0.90–1.45. The lining adds US$0.10 for jersey or US$0.18–0.30 for 180–220 gsm velvet. The insert adds US$0.20–0.55 for die-cut 30 kg/m³ EVA or US$0.12–0.25 for pick-and-pluck. Adhesive film is US$0.08–0.15.
Add it up: a small watch or thermometer case lands at US$1.10–1.60 of material, a medium headphone or BP monitor case at US$1.60–2.80, and a large drone fly-more or tool case at US$2.90–4.80. Material is typically 40–55% of the FOB price.
Labour, zipper and packaging
Labour runs 6–14 minutes per case depending on how many panels are bound and how many components are stitched in. At US$0.08–0.12 per minute that is US$0.50–1.60. Press time is machine cost rather than labour, and it falls with a heavier tool because the cycle is shorter.
The zipper is the second-largest component after the shell: a generic #5 runs US$0.18–0.30, a YKK #8 runs US$0.40–0.60 and a PU-coated waterproof YKK runs US$0.75–1.10. Packaging is small per unit and large in aggregate: poly bag US$0.03, hangtag US$0.05, printed sleeve US$0.25–0.45, and a US$0.30–0.55 share of the export carton.
How unit price falls from 100 to 5,000 pcs
Variable cost falls for three reasons: material nesting improves, the zipper is bought in larger rolls, and the stitching line learns the style. Fixed cost falls for one reason, which is that it is divided by more units.
- 100 pcs: below the 300 pcs minimum. Stock mould only, with a US$1.20–1.80 per-piece small-run surcharge and no mould credit.
- 300 pcs: US$4.22 / pc for the reference case, tooling separate.
- 500 pcs: US$4.00 / pc.
- 1,000 pcs: US$3.80 / pc.
- 2,000 pcs: US$3.55 / pc, with the mould charge credited.
- 5,000 pcs: US$3.22 / pc.
From 1,000 to 5,000 pcs the unit price falls US$0.58, about 15%. From 300 to 1,000 pcs it falls US$0.42, about 10%, and a further US$3.17 per piece of amortised tooling disappears. Volume helps the unit price; it helps the total far more.
Worked example: 300 pcs versus 2,000 pcs
Reference case: 5 mm 75D EVA shell, 1680D face, die-cut 30 kg/m³ insert, YKK #8 zipper, webbing handle, printed sleeve, new mould. Same specification at both quantities, so the only variables are volume and amortisation.
At 300 pcs
- Shell, face, lining and adhesive: US$1.73
- Die-cut insert: US$0.59
- YKK #8 zipper: US$0.45
- Labour, including small-run line setup: US$1.06
- Packaging: US$0.39
- FOB unit price: US$4.22, or US$1,266 for the run
- Tooling at US$1,360, amortised: US$4.53 / pc
- Sea freight, 1.2 cbm LCL: US$0.60 / pc
- Duty at an illustrative 5% of FOB: US$0.21 / pc
- Landed cost: US$2,869 in total, US$9.56 / pc
At 2,000 pcs
- Shell, face, lining and adhesive: US$1.54
- Die-cut insert: US$0.53
- YKK #8 zipper: US$0.43
- Labour: US$0.72
- Packaging: US$0.33
- FOB unit price: US$3.55, or US$7,100 for the run
- Tooling at US$360, because the mould is credited: US$0.18 / pc
- Sea freight, 8 cbm at US$95: US$0.38 / pc
- Duty at 5% of FOB: US$0.18 / pc
- Landed cost: US$8,575 in total, US$4.29 / pc
The per-unit FOB price falls 16%. The landed cost falls 55%, from US$9.56 to US$4.29, and most of that is the tooling denominator rather than the material. That is the honest argument for consolidating two small orders into one 2,000 pcs run, and the honest argument against ordering 300 pcs of a new design twice.
Change one assumption and the picture moves. Run the same 300 pcs on a cavity that is already in the library and the tooling line falls from US$1,360 to US$360, taking the landed cost from US$9.56 to US$6.23 per case on the same specification. The 300-piece order is only expensive when the design is new; on an existing mould it is a defensible first run.
Freight and duty: what is not on the FOB quote
A medium case packs at about 0.004 cbm and 0.9 kg. That makes 300 pcs 1.2 cbm and 270 kg, below the practical LCL minimum, so you pay for roughly 1 cbm plus US$120–160 of origin charges, about US$180 door to port. At 2,000 pcs you have 8 cbm at US$95 per cbm, about US$760.
Air freight changes the decision. 2,000 pcs at 0.9 kg is 1,800 kg chargeable; at US$5.20 per kg that is US$9,360, or US$4.68 per case, which is more than the material in the case. Air is for samples and for a launch that cannot wait 30 days, not for a 2,000 pcs replenishment.
Duty is a percentage of the customs value, set by HS code and destination; cases usually clear under HS 4202 at a rate between 3% and 7%. If your broker confirms 5%, that is US$0.21 per piece at 300 pcs and US$0.18 at 2,000 pcs, before any additional tariff your market applies. This is why the number to compare across suppliers is landed cost per piece at your real quantity: purchase cost, plus amortised tooling, plus freight, plus duty.
What to ask for in a quote
- The quantity the price applies to, and the break at the next quantity up.
- The specification written out: shell thickness and EVA density, face fabric, lining, insert, zipper brand and size, print method.
- Tooling itemised line by line, with the credit terms stated in writing.
- Incoterm, plus freight per carton and per cbm, so you can check it against a forwarder.
- Payment terms, sample cost, and whether the sample charge is deducted from the bulk order.
- Quote validity and the material price basis, because EVA sheet moves with oil and a 90-day-old quote is a guess.
Send a specification and a quantity and we will return this model filled in with your numbers, tooling credit included. Payment is 30% deposit and 70% before shipment, FOB Shenzhen or Yantian, with CIF and DDP available if you would rather compare landed cost directly.